Hi Folks, After the last few days of not doing anything..................

After breaking down on Tuesday on way to the Hospital, stopped at Kingsway and (it is booked in for Friday Morning),


So I just do not know how many days I will be able to work on the transit this week!. due to stomach pains and struggling to concentrate and find any motivation!.

So fingers crossed I will have a good day today.

On way to Hospital Tuesday, I stopped in and brought 10 x 3x2 timber (hopefully the last) and it almost cleared the bank out ...............


But as I cannot carry on, without it, It was a necessary purchase, so hopefully I can get  a lot of the bed frame finished this week (Finally)

There is an awful lot of painting needing doing, but I only have  about 1/3rd of the can left, But I will get it used at some stage this week. 

If we have a good weekend I will buy another tin of White Silk paint next week.

To save money, It has been decided that we will re-use the old MDF boards, that we used on the old bed, after I put my knee thru the bed!!

The MDF will need cutting to shape, ( as it used to be wedged in by both sides, with the mattress on top, which gave us somewhere for the electronics and my Sleep machine. )

 

I will drill some air holes in them, to stop any mattress sweating.

There will be less space behind the bed, than I had hoped, just how much, we will have to wait n see...

Again I did not get to work on the transit!
I tried 3 times but could not walk thru the door :( :( 

So went back to bed in disgust..........................

Updated - Jobs pencilled in till Sunday

Boy has this list grown !!

I will delete completed jobs a week after they are finished !

Green - Completed job

purple - job in progress

Yellow - Job Description
Blue - new jobs added or not started

 

 

1. Buy more 2x3 from Andrews - Done 07/03

1A. 

1B. 

2. cut n fit bed head board panel to driver side side of van - Started 25/02

2A. 

2B. glue foot panel board passenger side in place - Started 25/02

3. Measure & Cut front 9mm ply panel for bed - Started 25/02

3A. Measure & cut storage hole in 9mm ply for bed - 

3B Fit & secure bed front 9mm panel - 

5. add extra supports to mount the sink. - hopefully be completed next Monday
6. Panel the bulkhead battery frame work.
7. 
8. Get MDF from old bed from green shed and cut to fit the bed frame - 

9. 35. Paint the Passengers side rear wheel panel -  

10. need some material for bed header cover - use some DODO insulation as filler - 

11. 

12. 

13. inside kitchen cupboard by bed, need strengthening, so we can bolt the kitchen and the bed together -  

14. make base for bathroom sink 9mm ply - 

15. 

16. measure and cut 1st roof panel 3mm ply - just some clips to add
17. Finally screw roof panel into place. - Panel clips have arrived
18. install sink tap & waist pipe - REMOVED to install wall boarding

18A. 2nd panel run light wires thru roof frame. - 

18B. 3rd panel run light wires thru roof frame. - 

18C. 4th Panel run light wires thru roof frame. - 
19. scobby doo's for blue cover for Mattress to protect it.
20. mount bathroom sink extra mounts - 

21. bring mattress down, when bed frame is made

22. add mount points to transit frame for bed frame

23. re-assemble the framework onto raised toilet area - 
24. sand back to bottom of the bathroom wall, so panels match the upright

25. Paint the Drivers side rear wheel panel -  

26. - put bathroom door frame back. - 
27. remove grill from kitchen unit and repair and put back - Removed, Lynne has started washing it.
28. water pumps screw to back of kitchen unit - 
29. remove sink and drainage board - 
30 buy some sealant gaskets for kitchen unit and install - arrived - not yet ready to use
31. refit cooker & sink & drainage board -  
32. move kitchen to its final location - Now needs Bolting in place (25th/02)
33. bolt the kitchen in place.
34. 

35. drivers side wheel wheel build framework & board over - Started 26/02 Framework finished - Just needs boarding.

37. Passenger side wheel wheel build framework & board over - Started 02/03

38. Cut passenger side floor batton.

39. Rear Drivers side sound proofed bottom half -  Finished!! 25/02
40. Added DODO insulation and more sound proofing -  Finished!! 25/02
41. Cut out storage hole in bed side panel. - 

42. needs sanding and prepping for painting white - 
43. Paint the panel - 
44. Buy large tin of white silk paint
45. 

46. 
47. Add guide lines for storage containers to floor - 
48. needs prepping for paint

49. Paint

50. 
51. 
52. Buy extra Containers needed for under bed storage. - 

53. Measure area and test fit Generator (remove when tested) -
54. 

39. Kev's workshop - Make some brackets and install roof rack on roof of transit. (Funds ring fenced) - Booked in on Tuesday 14th Feb.


39A. Kev's workshop - If time and funds allow, get water tanks installed underneath and plumbed into the back. (have some funds available but I know it will not be enough!) - Booked in on Tuesday 14th Feb.

 

Double Bonus job, to have worked out and cut the bed frame & have it mounted!